THE National Grid Corporation of the Philippines (NGCP) placed the Visayas grid under red and yellow alerts on Tuesday following a surge in electricity demand and a fresh wave of unexpected power plant shutdowns.
According to the NGCP advisory, a yellow alert was raised from 3:00 p.m. to 5:00 p.m. and again from 6:00 p.m. to 8:00 p.m.
A more critical red alert was enforced between 5:00 p.m. and 6:00 p.m., during which peak demand was projected to hit 2,545 megawatts (MW) against an available capacity of only 2,468 MW.
The grid operator reported that 25 power plants were on forced outage, while another 22 plants operated at derated capacities, taking a total of 685 MW offline.
The supply deficit was primarily triggered by the unavailability of the Panay Energy Development Corporation Unit 3 and KEPCO SPC Power Corporation Unit 1, alongside reduced power imports from Mindanao due to scheduled plant maintenance in that region.
Under industry guidelines, a red alert is declared when supply falls short of consumer demand and required regulatory buffers.
Meanwhile, on a separate power sector development, the Energy Regulatory Commission (ERC) greenlit Northern Sun Power Inc.’s proposed PHP 1.11-billion transmission facilities.
Released Saturday in a decision dated October 14, the ERC authorization allows the firm to build and own connection facilities for its 244-megawatt Currimao solar project—paired with a 337-megawatt-hour battery energy storage system—spanning Currimao and Paoay in Ilocos Norte.
The installation will link directly to the NGCP’s 230-kilovolt Pinili substation.